A mutual action plan (MAP) is a shared, dated plan that buyer and seller agree together, covering every step from now to the buyer's go-live. Each step has an owner on one side or the other and a date. The point is not the document. The point is that the buyer has said, in writing, what has to happen on their side and when.
Also called a mutual close plan, joint execution plan, success plan or customer success plan, depending on the company. The mechanics are the same.
Why a MAP works when a close plan does not
A close plan is the seller's private guess at how the deal will close. A MAP is the buyer's own plan, written with the seller. That difference does three things:
- It surfaces the steps the seller cannot see. Security review, legal, procurement, budget sign-off and the board meeting that has to approve spend. Buyers know these exist; sellers often learn about them in the last week of the quarter.
- It puts names on the buyer's side. "Legal reviews the MSA" becomes "Priya in legal reviews the MSA by the 14th". A named owner is a person you can now build a relationship with.
- It makes slippage visible early. When the buyer misses a step, both sides see it the same day, not when the close date quietly moves.
What goes into a mutual action plan
| Section | What it holds | Why it matters |
|---|---|---|
| Goal and go-live date | The business outcome the buyer is buying and the date they need it working by | Anchors every other date to the buyer's deadline, not the seller's quarter end |
| Decision criteria | What the buyer said they will judge the decision on | Keeps the evaluation on agreed ground |
| Milestones | Discovery, technical validation, business case, security review, legal, procurement, signature, kickoff | The sequence. Most deals slip in the last four |
| Owner per step | A named person on the buyer side or seller side | Accountability, and a map of who you need a relationship with |
| Date per step | Agreed, not suggested | Lets both sides see slippage on the day it happens |
| Status | Done, on track, at risk, blocked | The one column that gets updated every week |
| Stakeholders | Everyone who signs, approves or can block | Your buying committee, confirmed by the buyer |
A mutual action plan template you can copy
Work back from the go-live date. A simple version for a mid-market software deal might look like this; adjust the steps to how your buyer actually buys.
| Step | Owner | Side | Target date | Status |
|---|---|---|---|---|
| Confirm goals, success criteria and go-live date | Champion and AE | Both | Week 1 | Done |
| Technical validation or pilot | Buyer IT lead and SE | Both | Weeks 2 to 4 | On track |
| Business case shared with economic buyer | Champion | Buyer | Week 4 | On track |
| Economic buyer meeting | Champion and AE | Both | Week 5 | At risk |
| Security questionnaire returned | Seller security team | Seller | Week 5 | On track |
| Legal review of MSA and DPA | Buyer legal | Buyer | Weeks 5 to 7 | Not started |
| Procurement and vendor onboarding | Buyer procurement | Buyer | Weeks 6 to 8 | Not started |
| Signature | Economic buyer | Buyer | Week 8 | Not started |
| Kickoff and onboarding plan | CSM and champion | Both | Week 9 | Not started |
When to introduce it
After discovery has confirmed there is a real problem and a real date, and before the technical evaluation starts. Too early and it reads as presumptuous; too late and it is a closing tactic the buyer can see through. A natural opening: "To hit your go-live date, here is what we have seen need to happen. Can we check it against how your team actually buys?" Then let the buyer edit it.
Why most mutual action plans fail
- The buyer never edits it. A plan the seller wrote and the buyer nodded at is a close plan with a new name.
- It only has seller-side steps. If every owner is on your team, the plan measures your activity, not the buyer's commitment.
- Steps on the buyer side have no names. "Procurement" cannot be called. A person can.
- Nobody updates it. Review it on a fixed weekly call, or it stops surfacing problems, which was the reason to build it.
- It lives in a file nobody can find. Put it somewhere both sides can open without asking: a shared doc, a deal room, or the tool your team already uses.
Every name on the plan is a thread
The stakeholder and owner columns are the most useful part of a MAP, because each name is someone the deal depends on and you may not know yet. A plan with eight buyer-side names and one active relationship is still a single-threaded deal. Use the plan as your multithreading checklist: for each name, who on your side, or among your customers, investors and partners, already knows them? Boomerang's agent, Rudy, answers that for each person on the plan and drafts the introduction for the connector to send from their own account.
If you qualify with MEDDIC, the MAP is where the Decision Process letter becomes concrete: the decision process is the list of steps in the plan.
Frequently asked questions
What is a mutual action plan?
A shared, dated plan that buyer and seller build together, listing every step, owner and date from today to the buyer's go-live. It turns a forecast date into a sequence both sides have agreed to, so slips show up early.
What should a mutual action plan include?
The goal and go-live date, the buyer's decision criteria, the milestones (validation, business case, security, legal, procurement, signature, kickoff), a named owner and agreed date for every step, a status column, and the full list of stakeholders who sign, approve or can block.
What is the difference between a mutual action plan and a close plan?
A close plan is the seller's private view of how a deal will close. A mutual action plan is written with the buyer and shared with them, so the buyer's own steps, owners and dates are explicit and agreed.
When should you introduce a mutual action plan?
After discovery has confirmed a real problem and a real date, and before the technical evaluation starts. Present it as a draft built from how similar buyers have bought, and ask the buyer to correct it.
Why do mutual action plans fail?
Usually because the buyer never edits them, every step is on the seller's side, buyer-side steps have no named owner, or nobody updates the plan after the first week.
Is a mutual action plan the same as a success plan?
The mechanics are the same: shared steps, owners and dates. Teams usually say mutual action plan before signature and success plan for the post-sale onboarding and adoption steps. Many teams keep one document that runs from evaluation through go-live.